Question: The requirements traceability matrix: Question 2 0 options: is an output of the Control Scope process. is an output of the Direct and Manage Project

The requirements traceability matrix:
Question 20 options:
is an output of the Control Scope process.
is an output of the Direct and Manage Project Work process.
helps to detect the impact of any change or deviation from the scope baseline on the project objectives.
is an output of the Validate Scope process.