Question: The Responsibility Matrix (or RACI Table) is used to help match the action for a task with a specific resource (or resources) on the project.
The Responsibility Matrix (or RACI Table) is used to help match the "action" for a task with a specific resource (or resources) on the project. When creating the RACI Table, select the CORRECT answer from the choices below that best summarizes the description listed here: This annotation identifies the person who is told when the task has been completed, or is now in progress - but this person is not actually "doing" any work on the project.
Group of answer choices
A. ( R ) - Responsible
B. ( C ) - Consulted
C. ( A ) - Accountable
D. ( I ) - Informed