Question: The road construction project is twelve weeks behind schedule with ten team members working on it. Five of these team members are working on the

The road construction project is twelve weeks behind schedule with ten team members working on it. Five of these team members are working on the Critical Path related items. What is the Slack of the Critical Path?

Negative twelve weeks

30

0 (Zero)

Not enough information