Question: the same table is used for all questions Using Table 1, the variance for activity E is A. 2.25 B. 2.78 C. 1.00 D. 1.78

 the same table is used for all questions Using Table 1,
the variance for activity E is A. 2.25 B. 2.78 C. 1.00
D. 1.78 Using Table 1, the earliest finish time for activity C
is A. 4.0 weeks. B. 5.5 weeks. C. 9.0 weeks. D. 14.5
weeks. E. None of the above Using Table 1, the critical path
for the project consists of activities A. B-C-E.G B. A.E-G. C. B-F-G
D.A.D Using Table 1, how much slack is associated with activity C?
the same table is used for all questions

Using Table 1, the variance for activity E is A. 2.25 B. 2.78 C. 1.00 D. 1.78 Using Table 1, the earliest finish time for activity C is A. 4.0 weeks. B. 5.5 weeks. C. 9.0 weeks. D. 14.5 weeks. E. None of the above Using Table 1, the critical path for the project consists of activities A. B-C-E.G B. A.E-G. C. B-F-G D.A.D Using Table 1, how much slack is associated with activity C? A. 0.0 weeks. B. 1.0 weeks. C. 4.0 weeks: D. 5.5 weeks. E. None of the above Using Table 1, the expected time to complete the project is A. 16 weeks. B. 15 weeks. C. 19 weeks. D. 20 weeks. E. None of the above Using Table 1, the variance of the project's total completion time is approximately A. 2.78 B. 3.88 C. 3.94 D. 4.16 E. None of the above Using Table 1, the probability that the project could be completed in 23 weeks or less is approximately A. 0.87 B. 0.89 C. 0.91 D. 0.94

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!