Question: The sequential process presented below is entirely dedicated to the manufacture of product XYZ. This product has a weekly demand of 154 units. This process

The sequential process presented below is entirely dedicated to the manufacture of product XYZ. This product has a weekly demand of 154 units. This process works 40 hours per week. Calculate the theoretical number of seats required to balance this process to meet demand.

Your answer must be rounded to one decimal place. For example, if your answer is 8.46 posts, you would write 8.5The sequential process presented below is

A 5 min./u B 12 min./u 8 min./u D 4 min./u