Question: The Shapely Company uses the high-low method to determine its cost equation. The following information was gathered for the past year: Machine Hours Direct Labor
The Shapely Company uses the high-low method to determine its cost equation. The following information was gathered for the past year:
| Machine Hours | Direct Labor costs | |||
| Busiest month(June) | 11,250 | $ | 350,000 | |
| Slowest month (December) | 6,250 | $ | 270,000 | |
| If Shapely expects to use 8,500 machine hours next month, what are the estimated direct labor costs? |
$306,000.
$208,857.
$471,155.
$216,000.