Question: The shortest time required to complete an activity based on normal working hours and normal use of manpower, material and equipment is; Normal Time Crash

The shortest time required to complete an

The shortest time required to complete an activity based on normal working hours and normal use of manpower, material and equipment is; Normal Time Crash Time Maximum Crash Time Days Crashed QUESTION 13 Crashing sometimes has the reverse result of lengthening the project duration. True False QUESTION 14 Project Crashing shortens project duration by assigning more resources to critical tasks. True False QUESTION 15 Consider the above network and the following table for a project. What is the expected project duration