Question: The short-term scheduling activity called loading. OA) specifies the order in which jobs should be done at each work center B) assigns workers to

The short-term scheduling activity called "loading". OA) specifies the order in which

The short-term scheduling activity called "loading". OA) specifies the order in which jobs should be done at each work center B) assigns workers to jobs OC) assigns jobs to work centers OD) assigns workers to machines E) assigns dates to specific jobs or operations steps

Step by Step Solution

3.38 Rating (154 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Answer C assigns jobs to work centers This is the process of ass... View full answer