Question: The short-term scheduling activity called loading. OA) specifies the order in which jobs should be done at each work center B) assigns workers to
The short-term scheduling activity called "loading". OA) specifies the order in which jobs should be done at each work center B) assigns workers to jobs OC) assigns jobs to work centers OD) assigns workers to machines E) assigns dates to specific jobs or operations steps
Step by Step Solution
3.38 Rating (154 Votes )
There are 3 Steps involved in it
Answer C assigns jobs to work centers This is the process of ass... View full answer
Get step-by-step solutions from verified subject matter experts