Question: The space below you will be determining the allocation of work. The process is a sub shop that involves building a sub sandwich, assume one
The space below you will be determining the allocation of work. The process is a sub shop that involves building a sub sandwich, assume one sub per customer. The shop is open 10 hours a day. The typical demand is one customer every 5 minutes which requires 1 worker. The following describes the process:
| Process | Time | Preceding process |
| A) Take order, Select and cut bread | 20 sec | None |
| B) Put on meat, microwave prep | 60 sec | A |
| C) Place condiments | 70 sec | B |
| D) Cut sandwich and Bag product | 50 sec | C |
| E) Bag sandwich, collect funds | 30 sec | D |
a) Show the layout with a diagram using the letters and list times on diagram. Also determine the time it takes to make a sandwich. During lunch and dinner rush demand increases to one customer every 2 minutes. Now how many workers or work centers do you need? Use your diagram to show activity groupings. (5 pts)
c) Define numerically the minimum and maximum time to make a sandwich assuming all tasks remai constant?
Please draw a diagram for a)