Question: The standard deviation is 1 . 5 . Mean is 2 8 Consider the activities for Project Respawn Flash shown in the ( partially incomplete
The standard deviation is
Mean is
Consider the activities for Project Respawn Flash shown in the partially incomplete table below, along with expected times and variances of times. Assume time is measured in hours.
tableACTIVITYEXPECTED TIME,VARIANCE OF TIMEABCDEFGH
Based on what you got in previous questions, answer the two questions below:
ii Find the probability that the project will take more than hours. Give answer to the nearest percent
Steps:
Find value : sta sdard deviation; where is the target
Find the probability or area under the curve on ztable for zvalue found in step
Subtract the number from as we lok for the values greater than
iii Suggest a due date that gives the project a chance of ontime completion. due hours. Give answer to one decimal.
Steps:
Find score of look inside the table for and read corresponding first column and first row and call it
Calculate the target using: mean standard deviation.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock