Question: The stretched - S pattern observed during the project life cycle, for the most part, is a result of the _ _ _ _ _
The stretchedS pattern observed during the project life cycle, for the most part, is a result of the
a
principle that work expands to fill the allotted time
b
changing attitudes of the people who work in the project.
c
changing levels of resources used during successive stages of the project life cycle
d
difficulty in performing the individual activities of a project.