Question: The Supervisor has notified a Defect which has not been corrected at the time the Contractor submits an application for payment. The Price for Work

The Supervisor has notified a Defect which has not been corrected at the time the Contractor submits an application for payment. The Price for Work Done to Date assessed by the Contractor includes a completed item from the Bill of Quantities that has the notified Defect. Which TWO of the following statements are correct?
Select TWO options
The Price for Work Done to Date may include work that contains a notified Defect
The cost of correcting the Defect is a Disallowed Cost and should be deducted from the Price for Work Done to Date
The Price for Work Done to Date should not include any amounts for items which contain a Defect
The Contractor's application for payment should not include any amounts for items which contain a notified Defect
Completed work is work which is without notified Defects the correction of which will delay following work

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!