Question: The Systems Engineering Management Plan ( SEMP ) is a key management document that addresses several items. Which of the following is not included in
The Systems Engineering Management Plan SEMP is a key management document that addresses several items. Which of the following is not included in the SEMP?
Question options:
Description of management requirements including the activities to be managed
The interfaces to be maintained
Resource requirements for implementing the program
Manufacturing plan