Question: The table below displays the EST - ECT LCT - LST Information for a project. ( The time is measured by a unit of day.
The table below displays the ESTECT LCTLST Information for a project. The time is measured by a unit of day. B EST ECT LCT LST CONNO D E F G H Please use the information in the table to decide which options is are CORRECT. Difficulty Level Hard There may be more than one correct choice. Select ALL that apply. The completion time of the project is days. If activity starts on day the progress of the project will be delayed, Activity Ehas a slack time of day, The critical path of the project is ABDH
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock