Question: The table below displays the EST - ECT LCT - LST Information for a project. ( The time is measured by a unit of day.

The table below displays the EST-ECT LCT-LST Information for a project. (The time is measured by a unit of day.) B EST ECT LCT LST CONNO 26732992 D 915159 E 6897 F 610128 G 10131512 H 151818152 Please use the information in the table to decide which option(s) is (are) CORRECT. (Difficulty Level - Hard) There may be more than one correct choice. Select ALL that apply. The completion time of the project is 18 days. If activity starts on day 11, the progress of the project will be delayed, Activity Ehas a slack time of 1 day, The critical path of the project is A-B-DH

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!