Question: The table below includes processing times and due dates for five jobs. Processing Time (days 12 23 14 Days Due From Today 20 30 26

 The table below includes processing times and due dates for five

The table below includes processing times and due dates for five jobs. Processing Time (days 12 23 14 Days Due From Today 20 30 26 28 18 Job 10 If the jobs were conducted in this sequence, the average tardiness is (Points : 25) Approximately 25 days O Approximately 21 days O Approximately 17 days O Approximately 19 days