The table below provides machine usage and total machine costs for a company for the last 12 months.

Month Machine Hours Total Costs
January 524 $419,200
February 743 $594,400
March 967 $773,600
April 321 $256,800
May 948 $758,400
June 403 $322,400
July 369 $295,200
August 821 $656,800
September 794 $635,200
October 1,149 $919,200
November 440 $352,000
December 319 $255,519

Analyze the machine costs using the high-low method.

  1. Calculate the variable cost per hour (rounded to nearest dollar).
  2. Calculate the total fixed cost (rounded to nearest dollar).
  3. Express variable and fixed components using the equation Y=a+bXY=a+bX (use rounded numbers from 1. and 2. above.) (2 marks) Y=Y= ++ XX
  4. If a company expects to use the machine for 700 hours next month, what are the expected total costs? Make sure you carry through all digits and round your final response to th

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!