Question: The table below shows the processing time and due date for five jobs, which arrive in alphabetical sequence (A arrives first, E arrives last). Tasks
The table below shows the processing time and due date for five jobs, which arrive in alphabetical sequence (A arrives first, E arrives last).
| Tasks | A | B | C | D | E |
| Processing time (weeks) | 2 | 0.5 | 1 | 3 | 1.5 |
| Due date (weeks) | 3 | 6 | 4 | 5 | 2 |
1. If the jobs displayed in the table above are processed using the Earliest-Due-Date (EDD) rule, what would be the lateness of job B? Please show detailed work
2. If the jobs displayed in the table above are processed using the Earliest-Due-Date (EDD) rule, what would be the tardiness of job E? Please show detailed work
Step by Step Solution
There are 3 Steps involved in it