Question: The table below shows the processing times ( in days ) , and precedence requirements of the jobs that constitute a road construction project. 4

The table below shows the processing times (in days), and precedence requirements of the jobs that constitute a road construction project.
4
Job Processing time (days) Immediate Predecessors
A 4-
B 3-
C 7 A
D 11 A, B
E 4 C, D
F 9 D
G 6 E, F
H 6 F, G
What is the critical path of the road construction project?