Question: The table below shows the tasks required to assemble a widget in your factory. Currently, you have six employees each assigned to one task. Task
The table below shows the tasks required to assemble a widget in your factory. Currently, you have six employees each assigned to one task.
Task 1 Task 2 task 3 task 4 task 5 task 6
34 min. 7 min. 17 min 6 min 22 min 4 min
What is the maximum capacity for Task 3 (not the entire process)? (Express widgets per hour as 999.99)