Question: The table below shows the tasks required to assemble a widget in your factory. Currently you have six employees each assigned to one task. Task
The table below shows the tasks required to assemble a widget in your factory. Currently you have six employees each assigned to one task.
Task A Task B Task C Task D Task E Task F
Minutes Minutes Minutes Minutes Minutes Minutes
Which tasks will have Work In Progress inventory in front of them?