Question: The table below shows the tasks required to assemble a widget in your factory. Currently you have six employees each assigned to one task. Task

The table below shows the tasks required to

The table below shows the tasks required to assemble a widget in your factory. Currently you have six employees each assigned to one task. Task 1 Task 2 Task 3 Task 5 Task 5 Task 6 3 6 22 5 7 7 Minutes Minutes Minutes Minutes Minutes Minutes You are able to hire a 7th employee and utilize that employee in only one workstation. What is the new maximum number of widgets that can be assembled in one hour using the 7th employee? (calculate to two decimal places 999.99)