Question: The table below summarizes the major activities in a project. Employees can perform any function: a) Create a PERT chart and use it find the

 The table below summarizes the major activities in a project. Employees

The table below summarizes the major activities in a project. Employees can perform any function:

a) Create a PERT chart and use it find the critical path and the earliest possible completion time.

b) What is the maximum number of required employees on any day if all the activities are started as early as possible?

c) Is it possible to complete the project on time if the company has access to only seven employees per day?

#Employees Activity AB BC CD DE DO EF EG FG DI Description Plan Budget Framework Test cases definition Documentation Test case details Function design Database design Marketing plan Marketing execution Function details Function test Load testing Unit testing Final testing Time (days) 2 4 4 3 7 1 2 2 1 3 1 2 2 2 2 NNNNNNNN UJ GL LO LN JO NO 1 #Employees Activity AB BC CD DE DO EF EG FG DI Description Plan Budget Framework Test cases definition Documentation Test case details Function design Database design Marketing plan Marketing execution Function details Function test Load testing Unit testing Final testing Time (days) 2 4 4 3 7 1 2 2 1 3 1 2 2 2 2 NNNNNNNN UJ GL LO LN JO NO 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!