Question: The table below the project activities are shown a. Calculate the expected activity times (round to nearest integer). b. Construct an AON network based on
The table below the project activities are shown
a. Calculate the expected activity times (round to nearest integer).
b. Construct an AON network based on the Te
c. Calculate the activity slacks. What is the total project length? Make sure you fully label all
nodes in the network.
d. Identify the critical path. What are the alternative paths and how much slack time is
associated with each non-critical path?