Question: The table given below shows both the dependency and resource information of the activities in a construction project. Using the information given, level the resource

The table given below shows both the dependency and resource information of the activities in a construction project. Using the information given, level the resource requirement so that the number of workers utilized in a day is not more than X, and show the total number of workers for each day. Activity Predecessor(s) Duration (days) Crew Size Normal Minimum A - 5 A 1 B A 10 B 1 C A 10 C 1 D A 15 D 1 E B, C, D 5 E 1 A(normal crew size)=13 B(norm crew size)=10 C=(normal crew size)=7 D=6 E=11 X=19