Question: The table given below shows the precedence relations, and three time estimates (optimistic, most likely, and pessimstic) of activities of a project. Write down the

The table given below shows the precedence relations, and three time estimates (optimistic, most likely, and pessimstic) of activities of a project. Write down the mean and standard deviation of the project completion time.

Time (weeks)
Activity Immediate Predecessor(s) optimistic most likely pessimistic
A - 1 2 3
B A 3 5 7
C A 2 4 12
D B, C 4 5 12
E B 3 4 11
F B 1 3 5
G C, D 3 4 5
H E, F 2 3 4