Question: The table given below shows the precedence relations, and three time estimates (optimistic, most likely, and pessimstic) of activities of a project. Write down the
The table given below shows the precedence relations, and three time estimates (optimistic, most likely, and pessimstic) of activities of a project. Write down the mean and standard deviation of the project completion time.
| Time (weeks) | ||||
| Activity | Immediate Predecessor(s) | optimistic | most likely | pessimistic |
| A | - | 1 | 2 | 3 |
| B | A | 3 | 5 | 7 |
| C | A | 2 | 4 | 12 |
| D | B, C | 4 | 5 | 12 |
| E | B | 3 | 4 | 11 |
| F | B | 1 | 3 | 5 |
| G | C, D | 3 | 4 | 5 |
| H | E, F | 2 | 3 | 4 |