Question: The table on the right is the same as the one shown on Activity Duration (days) Predecessor Canvas Midterm Exam. It is copied here for

The table on the right is the same as the one shown on Activity Duration (days) Predecessor Canvas Midterm Exam. It is copied here for your None convenience. For detailed instructions, please refer to B 10 None Canvas Midterm Exam. 8 None D 14 A You can copy and paste the arrow below to make it a E 6 B little easier to draw network diagram. F 6 C G 10 F H 5 D, E 1 00 F H. K 10 1, J (A) 20 points A 2 D 14 H 5 J 8 3 3 B 10 E 6 G 10 K 10 C 8 F 6 8 (B) 2 points What is the critical path for the project above? (List all activities that are on the critical path in the correct order.) How long is the critical path? days
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
