Question: The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates. Task Length Predecessor Optimistic
The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
| Task | Length | Predecessor | Optimistic | Most Likely | Pessimistic |
| A | 7 | 6.1 | 7 | 7.5 | |
| B | 4 | A | 2.5 | 4 | 6 |
| C | 8 | A | 6.7 | 8 | 8.75 |
| D | 3 | B, C | 2 | 3 | 4.5 |
| E | 2 | B | 1.5 | 2 | 2.3 |
| F | 8 | D, E | 7.3 | 8 | 8.7 |
1. Calculate expected completion time for Task D.
2. Calculate completion time variance for Task B.