Question: The table shown below is for a project that is planned to be completed in 4 months. ( a ) What is the total planned
The table shown below is for a project that is planned to be completed in months.
a What is the total planned budget Budget At Completion of the project?
b Calculate SV CV SPI and CPI at the end of second month. Can you comment on the status of
the project? Please note that EV Completed times BAC
c Calculate the Estimate To Completion ETC
d Calculate the Estimate At Completion EAC using Method #
Month
Actual of the project
completed cumulative
Planned Value $ $ $ $
Earned Value $
Actual Cost $ $