Question: The table shows normal time, crash time, normal cost, crash cost and slack time of activities in a project. According to this table which activity

The table shows normal time, crash time, normal cost, crash cost and slack time of activities in a project. According to this table which activity must be crashed first? Assume there is only one critical path. (Only type the name of the activity