Question: The table will include activities with their normal and crash times along with their respective costs. The objective is to reduce the project duration by

The table will include activities with their normal and crash times along with their respective costs. The objective is to reduce the project duration by crashing activities at the least cost.
i. Project Completion Date
This can be determined by creating a network diagram, identifying the critical path, and summing the durations of the critical path activities.
ii. Crash the project to 10 weeks at the least cost b) Ross Builders Manufacturers steel storage sheds for commercial use. Leonard Ross, President of Ross Builders, is contemplating producing sheds for home use. The activities necessary to build an experimental model and related data are given in the following table 3 below:
Table 3
\table[[Activity,Normal time,Crash time,\table[[Normal cost],[($)]],Crash cost ($),\table[[Immediate],[Predecessor(s)]]],[A,3,2,1,000,1,600,-],[B,2,1,2,000,2,700,-],[C,1,1,300,300,-],[D,7,3,1,300,1,600,A],[E,6,3,850,1,000,B],[F,2,1,4,000,5,000,C],[G,4,2,1,500,2,000,D,E]]
i. What is the project completion date?
ii. Crash this project to 10 weeks at the least cost.
iii. Crash this project to 7 weeks (which is the maximum it can be crashed) at the least cost. (20 marks)
 The table will include activities with their normal and crash times

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!