Question: The tabulation and network diagram below represent a retooling project for a manufacturing company. The retooling is necessary to qualify for funding from a multinational

The tabulation and network diagram below represent a retooling project for a manufacturing company. The retooling is necessary to qualify for funding from a multinational agency for expansion of the plant. The retooling project was originally scheduled for a later date but has to be brought forward and crashed to meet the funding application deadline. [30]
a) Find the cost slope, maximum reduced time and the cost for the project for normal time. [5]
b) Hence, crash the project to meet a deadline of 18 days and determine the associated cost. [20]
\table[[Activity,\table[[Cost],[I.D.]],\table[[Maximum],[Reduced]],Direct Cost],[,Normal,Crash,],[,,,Time (d),Cost,Time (d),Cost,],[A,,,6,$500,4,$800,],[B,,,3,$200,2,$400,],[C,,,5,$500,4,$700,],[D,,,3,$200,1,$500,],[E,,,2,$300,1,$600,],[F,,,5,$400,3,$900,],[G,,,5,$150,4,$350,],[H,,,8,$550,4,$1750,]]
 The tabulation and network diagram below represent a retooling project for

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!