Question: The task ERP Testing has 6 weeks of duration and 18 weeks of work. Give a specific example of a resource allocation that the ERP
The task ERP Testing has 6 weeks of duration and 18 weeks of work. Give a specific example of a resource allocation that the ERP Testing task could have (assuming resources are allocated 100% of their available time)