Question: The task time for 4 tasks in a production line is 10, 15, 12 and 11 respectively (in minutes). If a day comprises of 8
The task time for 4 tasks in a production line is 10, 15, 12 and 11 respectively (in minutes). If a day comprises of 8 hours, the maximum production is
40
35
38
32
Can you please help me with this question? Thank you.