Question: The team has been able to implement the plan with some difficulties. Based on the information provided, how many web portals has the team implemented

The team has been able to implement the plan with some difficulties. Based on the information provided, how many
web portals has the team implemented by the end of the 15th week?
b. What is the EV?
c. What is the CV?
d. What is the BAC?
e. Assume that the planned length of the project is 45 weeks. What is the Planned Value at the end of week 15?
f. What is the EAC at the end of the 15th week