Question: The team has been working hard throughput the sprint, but time is running out. It's Wednesday, the sprint review is scheduled for Friday, and it

The team has been working hard throughput the sprint, but time is running out. It's Wednesday, the sprint review is scheduled for Friday, and it looks like the team won't be able to finish everything they planned. What should they do?

1. Focus on coding and leave the testing for next week

2. Re-schedule the sprint review for the following Friday

3. Move lower-priority user stories from the sprint backlog to the product backlog

4. Negotiate a sprint completion bonus to motivate the team to finish on time

5. Ask the lab manager to hire contractors to help

Step by Step Solution

3.42 Rating (155 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

In this situation the best option for the team would be Move lowerpriority user stories from the spr... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!