Question: The team has been working hard throughput the sprint, but time is running out. It's Wednesday, the sprint review is scheduled for Friday, and it
The team has been working hard throughput the sprint, but time is running out. It's Wednesday, the sprint review is scheduled for Friday, and it looks like the team won't be able to finish everything they planned. What should they do?
1. Focus on coding and leave the testing for next week
2. Re-schedule the sprint review for the following Friday
3. Move lower-priority user stories from the sprint backlog to the product backlog
4. Negotiate a sprint completion bonus to motivate the team to finish on time
5. Ask the lab manager to hire contractors to help
Step by Step Solution
3.42 Rating (155 Votes )
There are 3 Steps involved in it
In this situation the best option for the team would be Move lowerpriority user stories from the spr... View full answer