Question: The team on which you work has completed a recent iteration. Performance reporting will likely include all of the following except: A Comparison of stories
The team on which you work has completed a recent iteration. Performance reporting will likely include all of the following except:
A
Comparison of stories completed to plan within an iteration
B
Product backlog progress
Completed and expected stories for project
D
Percent complete rule