Question: The testing manager has signed off on the team's testing of the deliverables with the assurance that the team has properly conducted all testing and
The testing manager has signed off on the team's testing of the deliverables with the assurance that the team has properly conducted all testing and the deliverables were built according to industry standards government regulations and the customers requirement which of the following is true a. the team has verified the deliverables b. the team has accepted the deliverables c. the team has validated the deliverables d. the testing manager has accepted the deliverables