Question: The three - station work cell at TU Manufacturing is illustrated in the figure below. It has two machines at station 1 in parallel (

The three-station work cell at TU Manufacturing is illustrated in the figure below. It has two machines at station 1 in parallel(i.e., the product needs to go through only one of the two machines before proceeding to station2).
a. The bottleneck station is _____ with a bottleneck time of _____.[ Select ]["Station 1,30 minutes per unit", "Station 3,20 minutes per unit", "Station 2,10 minutes per unit", "Station 1,15 minutes per unit"]
b. The throughput time is _____.[ Select ]["4/hour","2/hour","28 minutes", "43 minutes"]
c. If the firm operates for one 8 hour day, the daily capacity of the work-cell is _____.[ Select ]["32","11.16","16","48"]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!