The three time estimates to,tm and tp of each activities of a project are given below:
\table[[Activity,to(days),tm(days),tp(days)],[1-2,2,7,12],[1-3,7,12,19],[2-4,3,12,21],[3-4,1,8,9],[4-5,6,15,30],[3-5,2,5,8]]
Draw the network diagram and find the expected duration and variance of each activity.