Question: The time estimate ( in weeks ) for the activities of a PERT network are given below. ( a ) Draw the project network and
The time estimate in weeks for the activities of a PERT network are given below.
a Draw the project network and identify all the paths through it
b Determine the expected project length.
c Calculate the standard deviation and variance of the project length.
d What is the probability that the project will be completed.
At least weeks earlier than expected time?
No more than weeks later than expected time?
e If the project due date is weeks, what is the probability of not meeting the due date?
f The probability than the project will be completed on schedule if the scheduled completion time is weeks
g What should be the scheduled completion time for the probability of completion to be Nov
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock