Question: The time for each activity to complete, the possible weeks by which that time can be reduced and the cost per week to decrease the

The time for each activity to complete, the possible weeks by which that time can be reduced and the cost per week to decrease the activity time. The cost to complete the project in normal time is $10,000 (40%)

Activity

Duration (wks)

Predecessor(s)

Crash weeks (possible)

Crashing cost per week

A

2

B

3

A

-

-

C

4

B

-

-

D

3

B

1

$580

E

4

B

2

$600

F

2

B

2

$510

G

4

D

2

$470

H

3

E

2

$580

I

2

F

2

$600

J

3

C,G

1

$560

K

5

D

-

-

L

6

F,H,I

1

$520

M

3

K

-

-

N

4

J, K

1

$410

O

5

L,M

1

$850

P

6

M, N

1

$750

  1. Draw the project network diagram for this project and identify those activities with slack number? (10%)

  1. What is the minimum time duration of the project? (5%)

  1. What is the critical path of the project? (5%)

  1. How much will be the most economical way to complete the project in 21 weeks? (10%) 19 weeks?(10%)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!