Question: The total cost, including normal time labor costs, for this hiring and layoffs plan is $ 2 6 5 , 5 0 0 ( enter

The total cost, including normal time labor costs, for this hiring and layoffs plan is $265,500(enter your response as a whole number).
b) Try a plan that holds employment steady (level strategy) by producing the average forecast for all four quarters (enter your responses as whole numbers).
\table[[Quarter,Forecast,Level Plan,\table[[Shortage],[(Units)]],\table[[Hire],[(Units)]],\table[[Layoff],[(Units)]]],[Production,\table[[Ending],[Inventory]]],[,,1,500,?bar(0),,,],[1,1,300,,,,,]]