Question: The total materials flexible budget variance can be split into: Select one: a . Fixed overhead and variable overhead b . Materials price variance and
The total materials flexible budget variance can be split into:
Select one:
a Fixed overhead and variable overhead
b Materials price variance and Materials efficiency variance
c Labor rate variance and Labor efficiency variance
d Variable overhead variance