Question: The total normal cost for a project is $5,000, the cost of supervision is $300 per day; penalty for delayed project is $100 per day,

The total normal cost for a project is $5,000, the cost of supervision is $300 per day; penalty for delayed project is $100 per day, for every day delayed beyond 16 days. Crash the duration of the project and find (a) the duration of the project with optimal cost and (b) the minimum possible du- ration for the project and the associated cost. The predecessor relationships and other requirements are tabulated in Table

Activity B C A D E F G H I J Predecessor(s) B B B A, C E A,C F,D H, I, G Normal Time (Days) 3 4 3 5 6 4 5 3 5 

Activity B C A D E F G H I J Predecessor(s) B B B A, C E A,C F,D H, I, G Normal Time (Days) 3 4 3 5 6 4 5 3 5 2 Crash Time (Days) 1 3 2 4 3 3 4 2 4 2 Incremental Crashing Cost (/day) 600 200 400 500 300 200 500 400 300

Step by Step Solution

3.34 Rating (157 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To solve this problem well use the Critical Path Method CPM to find the critical path and then identify the activities to crash in order to minimize t... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Law Questions!