Question: The unit network for small project involve 34 units, calculate the T of activity F if production rate for each activity is (buffer time =

The unit network for small project involve 34
The unit network for small project involve 34 units, calculate the T of activity F if production rate for each activity is (buffer time = 2): B D F Activity R Nm 1 2 1 3 4 14 14 18 b 10 4 d 4 4 14 14 18 18 23 0 4 f 18 5 23 a 4 0 4 4 9 9 17 5 e 8 5 10 10 18 Select one: O a. 38 O b. 26 O c. 42 O d. 30