The university IT team is working on the implementation of a new software system for enrollment. Using
No answer yet for this question.
Ask a Tutor
Question:
The university IT team is working on the implementation of a new software system for enrollment. Using the following table, complete the requested tasks: | ||||||||||
Time in days | Costs | |||||||||
Activity | Immediate Predecessor | Normal | Crash | Normal | Crash | |||||
A | - | 6 | 5 | $900 | $1,000 | |||||
B | A | 8 | 6 | $300 | $400 | |||||
C | A | 4 | 3 | $500 | $600 | |||||
D | B | 5 | 3 | $900 | $1,200 | |||||
E | C, D | 8 | 5 | $1,000 | $1,600 | |||||
a. Draw the network diagram noting normal and crash times. |
B. What is the critical path?
C. What is the minimum cost of crashing the project by 4 days? Would you recommend the team crash the project? Explain your calculations and position.