The US government has contracted with Raytheon to build its new Peacekeeper 2 ballistic missile. The project
Fantastic news! We've Found the answer you've been seeking!
Question:
The US government has contracted with Raytheon to build its new Peacekeeper 2 ballistic missile. The project has been laid out with durations (in weeks), predecessors, and costs included:
Activity | Normal Time (weeks) | Crashed Time (weeks) | Normal Cost | Crashed Cost | Predecessor(s) |
---|---|---|---|---|---|
A | 8 | 6 | $3,800 | $4,200 | - |
B | 9 | 7 | $6,300 | $7,000 | A |
C | 5 | 4 | $2,250 | $3,350 | B |
Which activity is the least desirable crashing candidate?
In order to reduce the project's overall duration by one week, at the lowest cost possible, which activity should you crash?
How much would it cost to crash the project by one week?
How much would it cost to crash the project by three weeks?
How much would it cost to crash the project by five weeks?