Question: The utilization of post-tensioned slabs would often require less reinforcing tonnage, although from a scheduling perspective, requires consideration of curing before the tendons can be
The utilization of post-tensioned slabs would often require less reinforcing tonnage, although from a scheduling perspective, requires consideration of curing before the tendons can be stressed and the formwork removed. Group of answer choices True False