Question: The variable cost per unit for a proposed project is $8.48 and the annual fixed costs are $27,400. These costs can vary by 5 percent.
The variable cost per unit for a proposed project is $8.48 and the annual fixed costs are $27,400. These costs can vary by 5 percent. Annual depreciation is $13,290 and the tax rate is 21 percent. The sale price is $13.29 a unit, 2 percent. If the firm bases its sensitivity analysis on the expected outcome, what will be the operating cash flow for a sensitivity analysis of 9,200 units?
A. $14,066.02
B. $11,554.50
C. $22,078.40
D. $18,385.60
E. $16,103.98