Question: the variance for activity C is weeks ( round your response to two decimal places ) C ) based on the calculation of the estimated
the variance for activity C is weeks round your response to two decimal places
C based on the calculation of the estimated times, the critical path is round your response to two decimal places D The estimated time for the critical path is round your response to two decimal places
E The activity variance along the critical path is weeks round you respond to two decimal places
F The probability that Hopkins hospitality will finish the project and weeks or less is enter as probability and round your response to three decimal